| Date |
Action/Document |
| 12-24 weeks before admission |
Appoint advisers and sign engagement letters
Agree timetable to admission
Commence drafting of accountants reports
Commence legal due diligence
|
| 6-12 weeks before admission |
Legal due diligence completed
Review and address any problem areas identified
Commence drafting admission document
Produce first drafts of other required documents
|
| 6 weeks before admission |
Circulate draft admission document
Commence legal verification of admission document
|
| 4 weeks before admission |
Working capital report circulated
Long form accountancy report finalised
Revised draft admission document
Draft placing agreement circulated
All other documents finalised |
| 2 weeks before admission |
Pathfinder board meeting
Pathfinder admission document published
Marketing: PR meetings and roadshow
|
| 10 days before admission |
10 day information submitted to London Stock Exchange |
| 1 week before admission |
Complete and approve all documents
Shareholders' meeting (if necessary), pricing and final board
meeting
Final admission document published
Final commitments received from institutions/allocation of
offer
Placing agreement signed |
| Admission week |
Submit documents to London Stock Exchange
Issue placing letters |
| Admission day |
IMPACT DAY
Dealings commence on AIM |
| Admission +1 |
Payment of flotation proceeds, net of fees and expenses, due to
the company |